@everydaykanban | @55degreesAB Follow us on social media /company/55degrees @55degreesAB @55degreesAB /55degreesAB /c/ActionableAgileAnalytics Apps that make it easier to get work done 🎉 From re fi ning work, to bringing external data into Jira, to improving work fl ows and creating reliable forecasts, 55 Degrees has apps to make your work less stressful.

Slide 3

Slide 3 text

#PM72 3 @everydaykanban | @55degreesAB Benjamin Franklin November 1789 “…IN THIS WORLD, NOTHING IS CERTAIN EXCEPT DEATH AND TAXES.”

Slide 4

Slide 4 text

Often forecasts are interpreted as certainties because we don’t tell them otherwise 4 #PM72 @everydaykanban | @55degreesAB CC BY-SA 3.0, https://en.wikipedia.org/w/index.php?curid=3422341

Slide 5

Slide 5 text

5 #PM72 @everydaykanban | @55degreesAB The 3 Gaps Outcomes Plans Actions

Slide 6

Slide 6 text

5 #PM72 @everydaykanban | @55degreesAB The 3 Gaps Outcomes Plans Actions ! Knowledge Gap Difference between what we would like to know and what we actually know

Slide 7

Slide 7 text

5 #PM72 @everydaykanban | @55degreesAB The 3 Gaps Outcomes Plans Actions ! Knowledge Gap Difference between what we would like to know and what we actually know ! Alignment Gap Difference between what we want people to do and what they actually do

Slide 8

Slide 8 text

5 #PM72 @everydaykanban | @55degreesAB The 3 Gaps Outcomes Plans Actions ! Effects Gap Difference between what we expect our actions to achieve and what they actually achieve ! Knowledge Gap Difference between what we would like to know and what we actually know ! Alignment Gap Difference between what we want people to do and what they actually do

Slide 9

Slide 9 text

6 #PM72 @everydaykanban | @55degreesAB Used with permission from Jim Benson A predictable response

Slide 10

Slide 10 text

7 #PM72 @everydaykanban | @55degreesAB EE4: Building an SSV Timeline Total expected hours Total hours Sam Jansen Expected hours Total hours Alexander Meynen Expected hours Total hours Tinus Michiels Expected hours Total hours Jeroen van Aert Expected hours Total hours Jef Van Den Bergh Expected hours Total hours Bob Verschueren Expected hours Total hours 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Tasks Subtasks wk h h h h h h h h h h h h h h Engineering a. Case SSV 1 i. Motor/ Solar panel analysis 7 4 3 ii. Gear ratio 15 2,5 2,5 10 2,5 2,5 2,5 2,5 iii. Choice of materials 10 5 1 1 1 1 1 5 1 iv. Frame design 30 15 2 1 1 1 15 1 1 v. Optimalisation (bisection method) 25 4 15 10 4 vi. Sankey diagram 10 12 10 vii. Production parts 20 10 12 10 viii. Construction 60 10 10 10 10 10 10 b. Case Simulink i. Simulation solar panel 24 4 4 4 4 5 4 4 10 ii. Simulation DC-motor 7 4 3 iii. Simulation race 6 1 1 1 1 1 1 c. Case SSV 2 i. Slope run test 24 4 4 4 4 4 4 ii. Simulation drive shaft 7 3 4 iii. Technical drawings 40 10 30 iv. Collision analysis 15 10 5 d. Race day 30 5 5 5 5 5 5 Enterprising e. Wikipage i. Company information 3 3 1 ii. SSV information 5 5 1 f. Name & Logo i. Design 2 1 2 ii. Engraving 6 3 3 g. Documents i. Plan of approach 4 2 2 2 2 ii. Work breakdown structure 4 2 2 2 2 iii. Gantt chart 10 1 5 3 5 3 iv. Cooperation contract 2 2 2 v. Case 1 document 45 5 5 15 5 5 15 5 5 15 5 vi. Simulink document 15 5 10 5 10 vii. Case 2 document 40 15 5 10 10 h. Wikipage i. Upload documents 5 5 1 ii. Blog 5 5 2 2 iii. Design description 6 3 3 iv. Final process report 5 i. Evaluation i. Test 1 30 5,00 5 5 5 5 5 ii. Test 2 30 5,00 5 5 5 5 5 iii. Peer assessments 1 total 548 0 92 27 92 25 92 21 88 22 91 25 90 25 Legende milestone responsibillity Gantt chart 1 Educating Weeks The workplace version of ruling it harder… CC BY-SA 3.0 - https://upload.wikimedia.org/wikipedia/commons/thumb/b/bf/AM4_Gantt.pdf

Slide 11

Slide 11 text

Deterministic Forecast 8 #PM72 @everydaykanban | @55degreesAB IT WILL BE DONE ON X DATE

Slide 12

Slide 12 text

Deterministic Forecast 8 #PM72 @everydaykanban | @55degreesAB IT WILL BE DONE ON X DATE •Communicates a single possible outcome

Slide 13

Slide 13 text

Deterministic Forecast 8 #PM72 @everydaykanban | @55degreesAB IT WILL BE DONE ON X DATE •Communicates a single possible outcome •Provides no probability of that outcome

Slide 14

Slide 14 text

Deterministic Forecast 8 #PM72 @everydaykanban | @55degreesAB IT WILL BE DONE ON X DATE •Communicates a single possible outcome •Provides no probability of that outcome •Appropriate only when certainty is assured

Slide 15

Slide 15 text

Probabilistic Forecast 9 #PM72 @everydaykanban | @55degreesAB THERE’S AN 85% CHANCE IT WILL BE DONE ON OR BEFORE 
 X DATE

Slide 16

Slide 16 text

Probabilistic Forecast 9 #PM72 @everydaykanban | @55degreesAB THERE’S AN 85% CHANCE IT WILL BE DONE ON OR BEFORE 
 X DATE •Two components: ‣ Range of outcomes ‣ Probability you’ll fall into that range

Slide 17

Slide 17 text

Probabilistic Forecast 9 #PM72 @everydaykanban | @55degreesAB THERE’S AN 85% CHANCE IT WILL BE DONE ON OR BEFORE 
 X DATE •Two components: ‣ Range of outcomes ‣ Probability you’ll fall into that range •Appropriate whenever uncertainty is present

Slide 18

Slide 18 text

10 Let’s create these probabilistic forecasts… #PM72 @everydaykanban | @55degreesAB Single Item Forecasts Multiple Item Forecasts

Slide 19

Slide 19 text

10 Let’s create these probabilistic forecasts… #PM72 @everydaykanban | @55degreesAB Single Item Forecasts Multiple Item Forecasts 📆 Fixed Date 📑 Fixed Scope 2 Types

Slide 20

Slide 20 text

For each, we can use the same simple data to calculate the probabilities 11 #PM72 @everydaykanban | @55degreesAB

Slide 21

Slide 21 text

Single Item Forecasts 12 #PM72 @everydaykanban | @55degreesAB How long will it take?

Slide 22

Slide 22 text

Single Item Forecasts 12 #PM72 @everydaykanban | @55degreesAB How long will it take? Finish Start

Slide 23

Slide 23 text

Single Item Forecasts 12 #PM72 @everydaykanban | @55degreesAB How long will it take? Finish Start Cycle Time: The total elapsed time it takes a work item to travel from start to fi nish

Slide 24

Slide 24 text

#PM72 13 @everydaykanban | @55degreesAB Cycle Time: The total elapsed time it takes a work item to travel from start to fi nish Single Item Forecasts (Finish date - start date) + 1

Slide 25

Slide 25 text

#PM72 13 @everydaykanban | @55degreesAB Finish Start Cycle Time: The total elapsed time it takes a work item to travel from start to fi nish Single Item Forecasts (Finish date - start date) + 1

Slide 26

Slide 26 text

Use a Cycle Time Scatterplot to calculate probabilities 14 #PM72 @everydaykanban | @55degreesAB

Slide 27

Slide 27 text

Use a Cycle Time Scatterplot to calculate probabilities 14 #PM72 @everydaykanban | @55degreesAB 50% of work took 7 days or less

Slide 28

Slide 28 text

85% of work took 16 days or less Use a Cycle Time Scatterplot to calculate probabilities 14 #PM72 @everydaykanban | @55degreesAB 50% of work took 7 days or less

Slide 29

Slide 29 text

15 #PM72 @everydaykanban | @55degreesAB by understanding your risk tolerance Choose a probability

Slide 30

Slide 30 text

15 #PM72 @everydaykanban | @55degreesAB Wrong as much as right… by understanding your risk tolerance Choose a probability

Slide 31

Slide 31 text

15 #PM72 @everydaykanban | @55degreesAB Wrong as much as right… Ask: What is the fallout if we fall outside of the probability? by understanding your risk tolerance Choose a probability

Slide 32

Slide 32 text

15 #PM72 @everydaykanban | @55degreesAB Wrong as much as right… Contains too many outliers Ask: What is the fallout if we fall outside of the probability? by understanding your risk tolerance Choose a probability

Slide 33

Slide 33 text

15 #PM72 @everydaykanban | @55degreesAB Wrong as much as right… Contains too many outliers Just the right balance? Ask: What is the fallout if we fall outside of the probability? by understanding your risk tolerance Choose a probability

Slide 34

Slide 34 text

16 #PM72 @everydaykanban | @55degreesAB probabilistically Deliver your forecast

Slide 35

Slide 35 text

16 #PM72 @everydaykanban | @55degreesAB 85% of the time we finish a 
 work item in 16 days or less 
 (from the day it starts) probabilistically Deliver your forecast

Slide 36

Slide 36 text

17 #PM72 @everydaykanban | @55degreesAB The underlying rule of thumb

Slide 37

Slide 37 text

Multiple Item Forecasts 18 #PM72 @everydaykanban | @55degreesAB When will they all be done?

Slide 38

Slide 38 text

Multiple Item Forecasts 18 #PM72 @everydaykanban | @55degreesAB Finish Start When will they all be done?

Slide 39

Slide 39 text

Multiple Item Forecasts 18 #PM72 @everydaykanban | @55degreesAB Finish Start Throughput: The total count of items that pass the de fi ned fi nish point in a given unit of time When will they all be done?

Slide 40

Slide 40 text

19 #PM72 @everydaykanban | @55degreesAB A Throughput Run Chart will show you the data But you need a Monte Carlo Simulation to calculate the probabilities

Slide 41

Slide 41 text

20 #PM72 @everydaykanban | @55degreesAB For Fixed Scope, use Monte Carlo: When

Slide 42

Slide 42 text

20 #PM72 @everydaykanban | @55degreesAB For Fixed Scope, use Monte Carlo: When There’s an 85% chance that we will f inish these 45 items on or before May 25

Slide 43

Slide 43 text

21 #PM72 @everydaykanban | @55degreesAB For Fixed Date, use Monte Carlo: How Many

Slide 44

Slide 44 text

21 #PM72 @everydaykanban | @55degreesAB For Fixed Date, use Monte Carlo: How Many There’s an 85% chance that we can f inish 67 or more items by then

Slide 45

Slide 45 text

22 #PM72 @everydaykanban | @55degreesAB For an entire portfolio, use Portfolio Forecaster!

Slide 46

Slide 46 text

23 @everydaykanban | @55degreesAB Summary

Slide 47

Slide 47 text

23 @everydaykanban | @55degreesAB • When more than one outcome is possible, probabilistic forecasts are necessary. Summary

Slide 48

Slide 48 text

23 @everydaykanban | @55degreesAB • When more than one outcome is possible, probabilistic forecasts are necessary. • Probabilistic forecasts show risk in 2 ways: 
 a probability (%) and a range. Summary

Slide 49

Slide 49 text

23 @everydaykanban | @55degreesAB • When more than one outcome is possible, probabilistic forecasts are necessary. • Probabilistic forecasts show risk in 2 ways: 
 a probability (%) and a range. • Choose a % that matches your risk tolerance Summary

Slide 50

Slide 50 text

23 @everydaykanban | @55degreesAB • When more than one outcome is possible, probabilistic forecasts are necessary. • Probabilistic forecasts show risk in 2 ways: 
 a probability (%) and a range. • Choose a % that matches your risk tolerance • Tools like ActionableAgile and Portfolio Forecaster exist to help you create these forecasts in minutes. Summary

Slide 51

Slide 51 text

24 #PM72 @everydaykanban | @55degreesAB Join us at the after party for demos of ActionableAgile, Portfolio Forecaster, and more Tuesday, June 14 19-21 CEST Register on the PM72 website!

Slide 52

Slide 52 text

@everydaykanban | @55degreesAB 🍦 Follow us on social media /company/55degrees @55degreesAB @55degreesAB /55degreesAB /c/ActionableAgileAnalytics Get your free trial of any app shown below via the Atlassian Marketplace!