Milestones
● Milestone 1 (October 14)
○ Feature to generate trips based on constraints
○ Working with Yelp API, adding client side support
○ Time Estimation: 20 hours
● Milestone 2 (November 4)
○ Feature to show and edit an overview of a selected trip
○ Working with Google maps API, adding client side support
○ Time Estimation: 20 hours
● Milestone 3 (December 2)
○ Feature to navigate between trip activities, offline support, and UI improvements
○ Working with Google maps, adding client side support and backend persistence
○ Time Estimation: 20 hours