Slide 5
Slide 5 text
The Build
5
Original plan was to start the refit in January but
building delays pushed everything back 6 months
Annex build allows for two must haves
◦ Dedicated electric supply for garage/brewery (10mm2)
◦ Proper brewery floor drainage and epoxy floor coating
Date Action
March New walls
April Concrete floor/drainage
May New stud wall between garage/brewery
June Hygienic wall cladding & epoxy floor coating
July/August Reinstall of brew kit incl. electric, plumbing
September Test Brew ? October – done!