Slide 63
Slide 63 text
Round 1: Utilisation
● Build team:
- You are 100% utilised, every 30 seconds you MUST switch project
(the facilitator will shout out ‘Change’)
● Test team:
- You can only verify the product once ALL pieces are combined and the product is handed over to you,
please use the test guidelines provided.
- Only once testing passes can the product be handed off and seen by the customer.
- If it breaks it goes back and MUST be fixed regardless of what else is being worked on.
● Customer:
- You must note the time when work starts on your request and the time when you receive your product
and provide the facilitator with the cycle time (in seconds)
- No talking to other customers, the builder or tester, you have a day job to do!
● Accountant:
- For every second products are not complete, they are costing us money.
Your job is to calculate how much this is, using the cost of delay figures provided