Knowledge of the closing process in large-scale products

Slide 3

Slide 3 text

NAVER MATOME

Slide 4

Slide 4 text

Agenda › Self-introduction › About NAVER MATOME › Tasks for closing › Problems › Lesson Learned › From now on

Slide 5

Slide 5 text

Self-introduction › Smartphone app : Property search app, etc. › NAVER MATOME: Maintenance operation , New service development › Feature phone website:Site for M1F1 etc. Development 3 Center Service Development Division 2 development N team › Mainframe: Government system. ( COBOL ) › Client-server : Government system, etc.(Pro*C, VB )

Slide 6

Slide 6 text

About NAVER MATOME

Slide 7

Slide 7 text

history 2010 • First anniversary • Start incentive program 2009 • Closed beta release • Service Releases • Mobile Release • Announcement Feature release • Social bookmarking collaboration started • Start displaying the number of accesses • Smartphone version release About NAVER MATOME

Slide 8

Slide 8 text

About NAVER MATOME 2009

Slide 9

Slide 9 text

About NAVER MATOME 2010

Slide 10

Slide 10 text

history 2012 2011 About NAVER MATOME • Major renewal • iOS App Release • Save Draft feature release • Topic Features Release • Android App Release • Group Summary Feature Release • Commercialization • Commencement of incentive system • Sponsored MATOME Release • Favorite Feature Release • Official MATOME Release • Add Category, "Category Sponsored" Release • Official Picture Release

Slide 11

Slide 11 text

About NAVER MATOME 2011

Slide 12

Slide 12 text

About NAVER MATOME 2012

Slide 13

Slide 13 text

history 2017 2015 • Monthly PV·UB record (3.1 billion PV·75.62 million UB) 2016 • Always SSL • Introduction of "deemed non-display system“ • improvement in disclosure requests 2014 • Smartphone version design renewal • Renewal of incentive system About NAVER MATOME 2013 • Jack Advertising Release • Business alliance with Yahoo! Japan • [Favorite Feature] Renewal 2018 • Business Succession to Next Library • Author Rank and Lisah release

Slide 14

Slide 14 text

history 2020 • Service Termination Notification • Suspension of new membership registration • End of service 2019 • Corporate "Mega Reach Video" released About NAVER MATOME

Slide 15

Slide 15 text

About NAVER MATOME Yahoo! topic Yahoo! trend reaction

Slide 16

Slide 16 text

About NAVER MATOME Twitter trend reaction At the time of service end notification. 2020/07/01 At the end of service. 2020/09/30

Slide 17

Slide 17 text

About NAVER MATOME Numbers

Slide 18

Slide 18 text

Total PV 171.8 billion PV About NAVER MATOME Numbers

Slide 19

Slide 19 text

Monthly Maximum PV 3.1 billion PV Total PV 171.8 billion PV About NAVER MATOME Numbers

Slide 20

Slide 20 text

Monthly Maximum PV 3.1 billion PV Total PV 171.8 billion PV Monthly Maximum UB 75.62 million UB About NAVER MATOME Numbers

Slide 21

Slide 21 text

Total Matome 1.8 million MATOME About NAVER MATOME Numbers

Slide 22

Slide 22 text

Total accounts created 340,000 Total Matome 1.8 million MATOME About NAVER MATOME Numbers account

Slide 23

Slide 23 text

Max View 3 million View About NAVER MATOME Numbers

Slide 24

Slide 24 text

single-user- created 26,000 MATOME Max View 3 million View About NAVER MATOME Numbers

Slide 25

Slide 25 text

single-user- created 26,000 MATOME Max View 3 million View Service Days 4,110 day About NAVER MATOME Numbers

Slide 26

Slide 26 text

About closing

Slide 27

Slide 27 text

Tasks for closing

Slide 28

Slide 28 text

Tasks for closing Overview › End notification period, etc. affects closing time › Some items need to be reported to the government. › 270+ total tasks

Slide 29

Slide 29 text

Tasks End date determined arrangement of rules and contracts man-hour estimate of development required for closing Notification method, timing consideration For Users announcement, timing Suspend new account activation Review Help Page incentive review For Partners cancellation procedure close response man- hour estimate contract termination timing arrangement Tasks for closing

Slide 30

Slide 30 text

Tasks End date determined arrangement of rules and contracts man-hour estimate of development required for closing Notification method, timing consideration For Users announcement, timing Suspend new account activation Review Help Page incentive review For Partners cancellation procedure close response man- hour estimate contract termination timing arrangement Tasks for closing

Slide 31

Slide 31 text

Tasks End date determined arrangement of rules and contracts man-hour estimate of development required for closing Notification method, timing consideration For Users announcement, timing Suspend new account activation Review Help Page incentive review For Partners cancellation procedure close response man- hour estimate contract termination timing arrangement Tasks for closing

Slide 32

Slide 32 text

Tasks End date determined arrangement of rules and contracts man-hour estimate of development required for closing Notification method, timing consideration For Users announcement, timing Suspend new account activation Review Help Page incentive review For Partners cancellation procedure close response man- hour estimate contract termination timing arrangement Tasks for closing

Slide 33

Slide 33 text

Problems & Lesson Learned

Slide 34

Slide 34 text

Problems › When can the service end. › The end notice may not be posted. › Can't watch the video. › Sudden server down. › What happens to the ongoing project.

Slide 35

Slide 35 text

Problems › When can the service end. › The end notice may not be posted. → Case 1 › Can‘t watch the video. → Case 2 › Sudden server down. › What happens to the ongoing project.

Slide 36

Slide 36 text

Problems Case1

Slide 37

Slide 37 text

Problems › Three months before closing Release of end notice posted on iOS app

Slide 38

Slide 38 text

NAVER MATOME iOS App › Requires an end notice period of 3 months. › Refurbishment period and Apple review period required to release iOS app. Problems

Slide 39

Slide 39 text

NAVER MATOME iOS App › Requires an end notice period of 3 months. › Refurbishment period and Apple review period required to release iOS app. Problems

Slide 40

Slide 40 text

Problems Sign in with Apple

Slide 41

Slide 41 text

Problems Sign in with Apple 2020.06.30 2020.04.30 → The day before the end notice publication date.

Slide 42

Slide 42 text

› Anyway, I submitted a store application › As a result, the store will be released on 7/1. Problems

Slide 43

Slide 43 text

Lesson Learned

Slide 44

Slide 44 text

Lesson Learned › We should have considered more about the potential impact of the platform we are using on our services.

Slide 45

Slide 45 text

Lesson Learned › Cases where service refurbishment may not be in control of release should have been addressed with greater importance. › We should have considered more about the potential impact of the platform we are using on our services.

Slide 46

Slide 46 text

Problems Case2

Slide 47

Slide 47 text

Problems › One month before closing YouTube search problem

Slide 48

Slide 48 text

Create Matome Articles › Choose a YouTube item › Find and add Problems

Slide 49

Slide 49 text

YouTube API administration screen › Queries is... at 0 Problems

Slide 50

Slide 50 text

YouTube API administration screen › Queries is... at 0 Problems

Slide 51

Slide 51 text

Problems Must comply with YouTube API Terms of Service.

Slide 52

Slide 52 text

Problems Must comply with YouTube API Terms of Service. The necessary renovations are: ·Change logo and icon ⇒ OK ·Change in how to use YouTube API ⇒ I don't know immediately how long it will take. ·Changes to NAVER MATOME Terms of Use ⇒ I can't respond immediately.

Slide 53

Slide 53 text

› Failure within a month of closing Problems

Slide 54

Slide 54 text

› Estimate of completion of first proposal exceeds closing timing › Failure within a month of closing Problems

Slide 55

Slide 55 text

› Estimate of completion of first proposal exceeds closing timing › Failure within a month of closing Problems › However, there are not many users of this function.

Slide 56

Slide 56 text

› Then, isn't it okay for the month to end? Problems

Slide 57

Slide 57 text

The words that PM said at that time. › The service is still working. › There may be some parts that make you feel relaxed when you finish, but I want to tighten my mind again. Problems

Slide 58

Slide 58 text

› Eventually, another plan will be implemented to resolve the issue. › I was able to respond for a week. › It's not perfect, but it was a response that could be selected at that time. Problems as a result

Slide 59

Slide 59 text

Lesson Learned

Slide 60

Slide 60 text

Lesson Learned › Service in progress until service termination.

Slide 61

Slide 61 text

Lesson Learned › Think about what you can do. › Service in progress until service termination.

Slide 62

Slide 62 text

Lesson Learned › Think about what you can do. › Continue the service comfortably until the end. › Service in progress until service termination.

Slide 63

Slide 63 text

From now on

Slide 64

Slide 64 text

From now on › Experience and knowledge accumulated through NAVER MATOME will be transferred to LINE