Upgrade to Pro — share decks privately, control downloads, hide ads and more …

Tom Beeley

Sponsored · Your Podcast. Everywhere. Effortlessly. Share. Educate. Inspire. Entertain. You do you. We'll handle the rest.
Avatar for Energy Now Expo 2013 Energy Now Expo 2013
February 21, 2013
54

Tom Beeley

The Timeline of Changes to the Financial Incentives - FIT's/RHI/ROC's- what happens next?

Avatar for Energy Now Expo 2013

Energy Now Expo 2013

February 21, 2013

Transcript

  1. About the CLA • CLA is the membership organisation for

    owners of land, property and businesses in rural England and Wales • 35,000 members own or manage around half the rural land in England & Wales • CLA lobby on behalf of members at EU, national and regional level • Provide independent advice on a wide range of policy issues • Access to member benefits
  2. What were the changes? • A series of reductions in

    PV tariffs • PV tariffs paid over 20 years • Introduction of a 3 tier tariff system for PV • Minimum building energy efficiency requirements for PV • Separate tariff band for multiple PV installations • Structured system of degression for PV and non-PV • Preliminary accreditation introduced from 1st December 2012 • Export tariff increase to 4.5p/kWh
  3. Feed in Tariff – PV Degression • Degression provides a

    structured reduction of tariffs • Tracks falling cost of technology • Maintains returns at target rates between 4.5 & 8% • Tariffs adjusted quarterly according to deployment in previous months • Reduces tariffs by 3.5% each quarter • Scope for flexibility depending on deployment levels • PV Degression is assessed in 3 capacity bandings
  4. Time table for tariff changes • New tariff rates announced

    2 months prior to changes • Tariff change dates for PV are 1st Feb, 1st May, 1st August, 1st November • E.g. Tariffs from Feb 2013- May 2013 were announced in December
  5. Simplified Table of PV Tariffs System size Tariff Rates 2012/13

    Total Installed capacity Tariff p/kWh 01/11/12-31/04/13 <4kW Higher 15.44 Middle 13.9 Lower 7.1 >4kW & <10kW Higher 13.99 Middle 12.59 Lower 7.1 >10kW & <50kW Higher 13.03 Middle 11.73 Lower 7.1 >50kW & <100kW Higher 11.5 Middle 10.35 Lower 7.1 >100kW & <150kW Higher 11.5 Middle 10.35 Lower 7.1 >150kW & <250kW Higher 11 Middle 9.9 Lower 7.1 >250 kW 7.1 Standalone 7.1 Export 4.5
  6. Feed in Tariff – Non-PV degression • Annual reduction in

    April each year starting from 2014 • Largest capacity band for each technology is linked to the RO • Tariff rates reduce by 5% each year • No scope to skip a step, but some flexibility in scale of degression • Tariff degression assessed separately for each technology • Opportunity for an additional degression step in October
  7. Current rates for non PV Tariff p/kWh Technology Prior to

    01/12/12 01/12/12 till 31/03/13 AD 250 kW or less 14.70 14.70 AD > 250kW but less than 500kW 13.60 13.60 AD >500kW 9.90 8.96 Hydro <15kW 21.90 21.00 Hydro >15kW and <100kW 19.60 19.60 Hydro >100kW and <500kW 12.10 (conditional on EU State Aid approval) 15.50 (after date of EU State Aid Approval) Hydro >500kW & <2MW 12.10 12.10 Hydro >2MW 4.90 4.48 Wind 1.5kW or less 35.80 21 Wind >1.5kW but not exceeding 15kW 28.00 21 Wind >15kW but not exceeding 100kW 25.40 21 Wind >100kW but not exceeding 500kW 20.60 17.50 Wind >500kW but not exceeding 1.5MW 10.40 9.5 Wind > 1.5MW 4.90 4.48 Export tariff 4.5
  8. Degression flexibility for non- PV • Degression rates that would

    apply at different levels of deployment • 2.5% if deployment in the previous year is <75% of the predicted value • 5% if deployment is in the range of 75-150% of the expected value; • 10% if deployment is in the range of 75-300% of the expected value • 20% if deployment is >300% of the expected value.
  9. Preliminary Accreditation • Preliminary accreditation introduced on 1st December 2012

    • Allows larger projects to ‘lock in’ the level of tariff they will receive • Projects gaining full accreditation receive the tariff appropriate at the date of pre accreditation • Applies to PV and Wind over 50kW & all Hydro and AD projects • Evidence of planning permissions, grid connection agreement & relevant licensing required • Valid for 6 months for PV, 12 months for wind and AD up to 2 years for hydro
  10. Preliminary Accreditation cont’d • Applications between 1st Jan and 31st

    March assigned the Tariff available at 1st April that year. • Be aware - For PV EPC requirements are not assessed at preliminary accreditation and changes to installation after accreditation will negate the tariff guarantee
  11. Overall picture for Feed in Tariffs • No changes are

    applied retrospectively • Tariff rates for PV have fallen, but so have costs • Export tariff rate increase • Structured degression reduces uncertainty for consumers and industry • Preliminary Accreditation reduces risk for larger projects • Feed in Tariff still a great deal for all technologies, especially when electricity generated utilised on site
  12. Renewables Obligation • Review of RO bandings took place in

    2012 • Number of changes were proposed • Exclusion of installations less than 5MW from RO was proposed • Carried out further consultation on PV banding with response in December 2012
  13. Outcome of the banding review • RO remains open to

    projects under 5MW • ROC allocations reduced • PV split into building and standalone categories • For PV rates better than consultation proposed
  14. Current & future bandings ROC’s per MWh Technology Current 2013/14

    2014/15 2015/16 2016/17 AD 2 2 2 1.9 1.8 Hydro 1 0.7 0.7 0.7 0.7 Onshore Wind 1 0.9 0.9 0.9 0.9 Building Mounted PV 2 1.7 1.6 1.5 1.4 Ground Mounted PV 2 1.6 1.4 1.3 1.2 Simplified table of ROC bandings
  15. Renewable Heat Incentive • Allocated budget of £860 million •

    Tariffs set by DECC to provide a target rate of return of 12% • Tariffs are index linked • Payments guaranteed for 20 years • Lessons learnt from FIT
  16. Picture so far • Slow initial uptake • 171 MW

    of installations accredited • 90% installations are biomass • Review scheduled for 2014 • Budgetary control mechanism consultation • Two further consultations undertaken to be implemented in Summer 2013
  17. Non Domestic Consultation • Consulting on the expansion of the

    scheme • Inclusion of direct air heating • Extension of support for biogas combustion to include systems over 200 kW • Sustainability requirement from April 2014 • Energy Efficiency Requirement
  18. Energy efficiency - more detail • Energy Efficiency requirements not

    a surprise • For non domestic buildings minimum level of building efficiency • District heating schemes heating less than 10 properties • District heating schemes heating more than 10 properties
  19. Domestic scheme • To support single domestic properties • Supports

    a range of technologies including biomass, GSHP, ASHP, Solar thermal • Final details of scheme not yet available • Opportunity for those off gas grid offers
  20. What will the changes mean? • Wider choice of technologies

    • Energy efficiency will need to be undertaken • Tariffs remain unchanged • Degression unlikely due to low uptake • Support for AD
  21. Overall picture for renewable heat • Great opportunity for those

    with heat demand and off the gas grid • Even better if you can provide some of your own feedstock for biomass as a free/ low cost fuel • Get in under the non-domestic scheme currently available if you can. • 2013 is the year for the RHI
  22. Conclusion • Renewable energy still viable • Good way to

    diversify income • Protect against future energy price rises • Business sustainability increasingly important • Utilise energy on site for best returns • Don't forget energy efficiency • Range of technologies to select from • 2013 and beyond offers great opportunities for renewable energy