in 1855 30 Offices across England & Wales Multi disciplined firm: Residential Rural Commercial Planning & Development Building Surveying Specialist Teams: Energy & Marine GIS CAD & Mapping Minerals and Waste Infrastructures Longstanding history and relationships with the farming sector
project delivery, including: feasibility studies, land assembly, finance and planning, overseeing procurement, construction and commissioning Specialists in anaerobic digestion, biomass, coal bed methane, energy from waste, hydro power, solar power and wind energy Clients include: Land and property owners, developers, energy companies, utility companies, investors in the sector, businesses with high energy demands Proven track record: 200+ ongoing projects Environmental Planning specialists Dedicated GIS CAD and Mapping team with specialist renewable energy software Strong market knowledge and experience of renewable energy sector, including manufacturers & their products Independent advice
potential mapping results for England and Wales Total number of barriers - 25,935 In England - 21,823 (782MW) In Wales - 4112 (396MW) Maximum power potential/MW - 1178 Average maximum power potential/kW - 45 Number of potential win-win opportunities - 4190 Number of low environmental sensitivity opportunities - 1092 Number medium environmental sensitivity opportunities - 5631 Number of high environmental sensitivity opportunities - 12,040
as per the original abstraction point on leat at 358m Weir repairs affecting an increase in the water level of the reservoir to the original level circa 800mm higher Siphon pipe installation Distribution screen box – HOF, turbine and river weir & maintenance of maximum efficiency 3.2km of pipe, 2 road & 1 watercourse crossing across 4 different tenancies over 2 ownerships! Water supply improvements, demand fed through new supply from settlement and filtering tank 80kw Turgo turbine, remote interface inclusive of controls system which varies frequency to find maximum ouptut for the actual flow and head of water available as it varies from day to day EASY!!!
licensing, Licensing (impoundment, abstraction and flood defence consents – estimation 3 years!!) – confused fish!!!!, careful record keeping and changes of personnel, loss of new water supply plans Planning – (Ecology, Bats, Water Voles & Archaeology) Tenure – (Landlord & Tenant relationships good – future reinstatement plans) Grid connection – (More expensive than anticipated, longer lead in times, contestable work) Civil works – (High variation in cost options against difficult balance in getting cost & quality) Finance – (Limited options, tax planning central to option choice – beware early repayments) FiT Changes – (Objective to be commissioned before end of March 2012)