  1. Sage 300 Construction & Real Estate (formerly Sage Timberline Office)

    Cost At Completion Pete Gallagher, CPA General Manager Aktion East
  2. Our Mission At Aktion Associates, being responsive, innovative and providing

    consistent delivery of leading edge technologies are the foundation of everything we do. We view our role as IT architects who partner with our customers to create a comprehensive technical roadmap that supports continued growth and profitability
  3. About Aktion • Founded 1979 • Privately held company •

    HQ in Maumee, Ohio • Supporting over 4,000 companies • 100 Employees
  4. Services • Managed Services – Application Hosting • Network Engineering

    • Software Engineering • Application Consulting • Website Design/eMarketing Solutions • Virtualization • Security • Cloud Technologies • Web Enablement • Collaboration • CRM • eCommerce • AktionLink Products • Custom Applications
  5. Industries of Expertise • Construction and Real Estate • Supply

    Chain • Architects and Engineers • Professional Service Businesses and Organizations • Non-Profit Memberships
  6. Technologies • Our strategy is to solve customer challenges with

    the technical tool set inherent in the customer’s platform of choice – IBM – Microsoft – Linux – HP
  7. Pete Gallagher, CPA • Timberline Construction Accounting & Property Management

    Certified • Over 20 years Timberline experience • Over 25 years in Construction Accounting
  8. Agenda • Purpose of PCAC • Psychology / Observed Problems

    • PCAC Methods • Forecasting in Sage 300 CRE: – Set up – Collect and Enter the projections – Integrate YOUR PCAC into Schedule of WIP
  9. Why this topic? • It’s GAAP / IFRS – “it’s

    an accounting thing” • “The computer should calculate it automatically” • “Project Manager’s don’t have time for paperwork”
  10. Quiz Answer: The day the bid is won PCAC =

    Estimate 1. Buy out 2. Internal change orders (C/O’s) 3. External C/O’s 4. Billable & Non-billable
  11. Importance • Revenue recognition • Risk management • Proactive project

    management • PM/Superintendent performance/bonus factor
  12. Challenge • PM who is responsible – “are you losing

    control” • PM compensation linked to projections • Logistics • Timing • Understanding why it is important
  13. Observed Problems • One PCAC method – Not appropriate for

    diverse and varying job types • Changing “estimate” – Lose true Change Order Trail • Accounting only • Project Manager responsibility only with no guidance – No Corporate Standard
  14. Why Misc. Worksheets? – Preserve true “Change” history on Estimate

    – Faster to enter Misc. WS versus process change orders – Manage Change Orders not manipulate them • Losing true CO picture
  15. Methods • Cost to Cost: – Cost to complete –

    Cost at completion – Reported Percent complete – Committed cost – buy outs
  16. Technology can help! • Multiple PCAC methods  Job types

    • PCAC separate from Estimate • Customized WIP reporting – Max(formula 1,formula 2, formula 3)
  17. Technology can help! • Retain history of overrides • Committed

    cost systems • Entry at different detail levels
  18. PCAC in Sage 300 CRE • Custom Descriptions – Determine

    field, name and level • JC Settings – Levels to track • Customize Miscellaneous Worksheets • Customize Schedule of Work In Progress – Out of the box: Total Estimate = PCAC • Document, educate, implement internally
  19. Custom Descriptions JC CC Amt 1 = Stored Material JC

    CC Amt 2 = Cost at comp JC CC Amt 3 = Cost to comp JC CC Amt 4 = Lab hrs to comp JC CC Amt 5 = Open JC CC Amt 6 = Open
  20. Job Cost Settings • Define Level of Cost Code to

    Track • Options varies on Cost Code Structure • Any level of Cost Code • Can track PCAC at Category
  21. Misc Worksheets • New Option: • Sage Excel-Based Reporting •

    Office Connector • Spreadsheet to collect projections • “Write” back to Misc. Worksheets • Understand: no transaction only record overwrite
  22. Schedule of Work in Process % Complete = Job Cost/Estimate

    Earned = % Complete x Contract If Billed > Earned, Billings in Excess If Earned> Billed, Cost in Excess
  23. Schedule of Work in Process SWIP Report Customization: 1. Add

    PCAC Column 2. Change: % complete = JTD Cost/PCAC (not JTD Cost/Estimate) 3. Earned = PCAC % Complete x Contract
  24. Tips • Numeric fields default to 0.00 • Use .01

    to force zero • Must maintain monthly • Timing is everything • Display codes/symbols on report to identify overrides • EDUCATE – EDUCATE - EDUCATE
  25. About Aktion – AEC Unit • Sage Business Partner •

    3rd Largest Sage in North America • Sage Chairman Level • 35% of total Aktion Business • Supporting over 2,000 Sage Customers • 35 Employees • Project Accounting Focus • From Estimate to Management
  26. Thank you for attending! • Pete Gallagher – Sage 300

    CRE - Construction Accounting Certified – Sage 300 CRE - Property Management Certified – Certified Public Accountant (NC) with 25+ years in Construction Accounting – 20+ years construction software experience [email protected] 704-971-3170 To find future Aktion web casts, please visit www.aktion.com/events
  27. Thank you for attending Pete Gallagher – [email protected] - 704-971-3170

    Dan Catlett– [email protected] – 703-777-8808 To find future Aktion web casts, please visit www.aktion.com/events
  28. Contact Us Info: • Aktion Support Line - [email protected]

    888-865-9425 • Pete Gallagher – [email protected] - 704-971-3170 • Upcoming events @ www.aktion.com