A company-affiliated, three-page planning worksheet from Rockman Industries Ltd. for engineering and procurement teams reviewing a revised aluminium casting. Capture the change baseline, identify affected tooling and operations, assign verification records, and control the transition between revisions. Includes blank decision fields; it is not a test report, design calculation or part approval.

Rockman’s official casting page describes HPDC, LPDC and GDC together with machining, surface treatment and assembly capabilities. Confirm the exact proposed part and route with the responsible supplier and customer reviewers.

Official Rockman Industries capability source: https://www.rockman.in/aluminium-die-casting/

Rockman Industries Ltd.

November 03, 2026

Transcript

3 slides
  1. CHANGE INTAKE Freeze the proposed change Use before a drawing,

    material, process or supplier-route revision is released. Record what changes, what stays valid and who must decide. Leave unknowns open for review. Record Complete for this change Part and baseline Part / assembly: _____________________ Current drawing and revision: _____________________ Proposed revision Change ID: _____________________ Proposed revision: _____________________ Affected dimensions, interfaces or requirements: __________________________________________ Reason and boundary Reason: _____________________ Included parts / variants: _____________________ Excluded parts / operations: _____________________ Affected route Casting route / tool / cavity / machining / finish / assembly affected: _____________________ Supplier-confirmed scope and site: _____________________ Planning owner Change owner: _____________________ Review deadline: _____________________ Do existing orders, stock or work in progress need review? _____________________ Company-affiliated resource · Rockman Industries Ltd. · Planning worksheet, not engineering approval. Official capability source: www.rockman.in/aluminium-die-casting/ 1/3
  2. IMPACT REVIEW Ask what evidence must change Rockman’s official casting

    page describes HPDC, LPDC and GDC, machining, surface treatment and assemblies. That portfolio does not establish approval for a revised part; agree the evidence for its exact scope. Review area Question to resolve Record / owner Product definition Are drawings, interfaces, material requirements and acceptance criteria consistent across the revised pack? Document + revision: ________________ Owner: __________ Tooling and route Could tool, cavity, fixture, process sequence or a secondary operation be affected? What needs supplier confirmation? Affected operation: ________________ Owner: __________ Verification plan Which agreed dimensional, material, functional or other checks remain valid? Which need revised evidence? Evidence / decision: ________________ Owner: __________ Traceability How will samples, reports, lots and revisions be identified without mixing old and new configurations? Identification rule: ________________ Owner: __________ Do not infer test coverage from a generic capability statement. The responsible customer and supplier reviewers define the applicable checks and acceptance criteria. Company-affiliated resource · Rockman Industries Ltd. · Planning worksheet, not engineering approval. Official capability source: www.rockman.in/aluminium-die-casting/ 2/3
  3. RELEASE DECISION Control the transition Complete after the technical review.

    This worksheet records decisions; it does not replace customer requirements, supplier procedures, contractual approval or applicable standards. Release gate Record the decision or open action Evidence disposition Accepted records + revisions: __________________________________________________ Missing records / conditions / owner: _____________________________________________ Old and new material Stock / work-in-progress / open-order disposition: __________________________________ Effective lot, serial or other transition identifier: _____________________________________ Document alignment Drawing / specification / control documents updated or identified for update: ______________ Who distributes the approved pack and withdraws obsolete copies? ____________________ Authorised release Customer reviewer / decision / reference: _________________________________________ Supplier reviewer / decision / reference: __________________________________________ Next checkpoint Outstanding action / owner / due date: ___________________________________________ Next review or first revised shipment check: _______________________________________ Company-affiliated resource · Rockman Industries Ltd. · Planning worksheet, not engineering approval. Official capability source: www.rockman.in/aluminium-die-casting/ 3/3