not to proceed?? Stage 5 Tender a.invite contractor to bid tender b. select contractor to win the tender Stage 7 Construction a. Manage site b. payment Stage 6 Contract Stage 8 Final certification (CF or CCC ) 10
after an architect’s drawing d. Early estimation: guidance by the developer b. completed c. used to compare : compatibility building cost and it’s design. e. To maintain the progress of the project. 11
structural Engineers • Mechanical and Electrical Engineers Co operate To make sure Design Building Construction price and Balance within the allocated budget and To ensures?? 24
Rate. When a client / developer propose for a new project investment, they would definitely want to know their profit returns. Profit return Cost effective!!! 26
Contractor to General Contractor Main Contractor Sub- Contractor Project • Divide the whole project into small part Domestic Nominated sub-contractor trade special 30
percentage and types of building elements. Total cost of building Building Cost Such as: • Material cost • Labour cost • Logistics cost i.e: company liability Such as: 32
A construction cost estimate serves one of the three basic functions: design bid control bid monitoring the project during construction, competitive bidding or negotiation encountered run parallel with the planning and design 35
b. Floor Area Method c. Cubic content method Have plan, measurement, information such as size, specification Have plan, measurement, information such as size, height specification & more details 3 types: 37
a completed school building = RM 100,000.00 Building Occupancy = 100 students Therefore, cost per unit occupancy (students) = RM 100,000.00 / 100 = RM 1, 000.00/ occupancy 38
the estimation for a new school building is feasible. For example, if a school building Therefore, estimated cost price : 200 students = 200 x RM 1, 000.00/occupancy = RM 200,000.00/occupancy 39
The client has a price projection of the building based or quantity, occupancy, etc. 3. Suitable for similar projects like hospitals, schools, stadium, and theatres. 40
measurement of the length and width is taken from one external wall to other external wall Wall Plan Length = 15.0 m Width= 6.0 m External wall surface Internal wall surface 43
priced at RM 200.00 per square meter, therefore the price rate for the proposed building should be roughly around: Floor Area x price rate/m² = 90.0 m² x RM 200 =RM 18,000.00 45
Unit valuation method 2. Easy and time effective 3. The calculation technique quit simple and easy. 1.1.4.2 Disadvantages of Floor Area Method: 1. Does not take building height into consideration 2. The price is still not accurate as it based on floor area only. 3.Not accurate because it is only roughly calculation. 55
is more or less the same as the Floor Area Method. The way to obtain the volume of the building is to multiply the height of the building with the floor area. Measurements are obtained from architectural drawings. However, the height of the building depends to the type of roofs used on each building. 56
ROOFS Gable roofs are roofs that have an inclination of more than 15 degrees. There is also cross hipped gable roofs. i. Pitch Roof Pitch of roof > 15 ̊ from horizontal line Can divide into 2 types of pitch - Full pitch - Half pitch 57
T ) = 3.2 m Height of building ( H ) = 18.0 m (Until on the top of pad footing) Formula of using roof area ( h ) h = ¾ x T Height = H + (h) = 18.0 m + (¾ x T) = 18.0 m +( ¾ x 3.2 m) = 18.0 m + 2.4 m = 20.4 m 63
T ) = 3.2 m Height of building ( H ) = 18.0 m (Until on the top of pad footing) Formula of using roof area ( h ) h = ½ x T Height = H + (h) = 18.0 m + (½ x T) = 18.0 m +(½ x 3.2 m) = 18.0 m + 1.6m = 19.6 m 64
roofs with an inclination of less than 15°. There are two types of flat roofs, one is fully flat roof and the other is flat roof with parapet walls. The total building height fully flat roof is measured from the Surface of the footing to the plus by 0.6 m 65