Share
Embed
Transcript
61 slides
-
UNIT 2:Build Up Rate Aim/Objective: To explain the requirement and
uses of: • the price rates • schedule of rates • base of price rate calculation Such as: • Materials • Labours • plants/equipment • overheads & • profits. -
Build Up Rate Aim/Objective: To solve the requirement and uses
of: • the price rates calculation For • Concrete work • Excavation work • Manual • machine use -
Build Up Rate Aim/Objective: To solve the requirement and uses
of: • the price rates calculation For • brickwork • Reinforcement work -
Introduction There are thousands item of work involved in the
construction work . Contractor will use the technique and method: to complete the work to make sure the project will success. -
Contractor: Will use technique & method the to complete the
work in the site Which is include the application of: • Material • labour & • tools To make sure -
Therefor; there are needs the contractor’s expenses of money. Contractor
: who have a lot of experience in the construction site not facing a lot of problems because: the previous information and data about the works will help them: o in the money expenses within the construction period. -
However; the price for every elements in the construction:
will always change or fluctuate in every time. -
It is depend to the: ii. labour problems or labour
prices. iii. tax. -
It is depend to the: iv. Government policies. v. regulation
by the Local Authority. vi. etc. -
Therefor: the knowledge of : material cost labour
cost labour market plant or equipment are very important to: support the contractor and professional members to: decide the most reasonable price for every element of the construction. -
The importance and uses of Build up rates in Estimating
work. The professional members such as: Quantity Surveyor(Q.S) :will use the build up rate in the design stage. to get the estimate for the project. -
The importance and uses of Build up rates in Estimating
work. Q.S will get the estimate for the project for the several purpose such as: 1.to know the budget from the Client 2.To know the appropriateness of design(suitable) based on the client’s budget. 3.As the information, data and the record for the forecast projects. -
BUILD UP RATES Basic Of Built-Up Rate Calculation Need.
a. Material cost b. Labour cost c. Mechinary and tool / equipment cost d. Overhead cost e. Profit cost -
BUILD UP RATES Condition: Not all the item
in the construction work must include all the above factor. It’s based on the type dan method of work will proceed on site. -
BUILD UP RATES Example: a) Excavation work manually.
Only labour cost, overhead and profit of the company must be considered. No material cost involve. -
BUILD UP RATES Example: b) Brickwall work. material
cost involve. Only labour cost, overhead and profit of the company must be considered. -
BUILD UP RATES Example: c) Concrete work by machine.
All five(5) costs above involve. • Materials • Labours • plants/equipment • overheads & • profits. -
Uses And Requirement of Build Up rates 1. To know
breakdown of the cost 2. To price up cost 3. Get budget 4. To know overhead 5. To know the construction building cost -
Basic price of materials Transportation or delivery cost to
the site Storage cost Wastage and shrinkage or damages cost Material Cost -
Basic price of materials Price there are not
include the profit, transportation cost and other cost. Price from factory or from supplier. Material Cost • Market price -
Basic price of materials Basic price will fluctuate from
time to time and from one place to another place. North and South – different effects to the basic price. Material Cost • Fluctuation price -
Transportation or delivery cost to the site. Delivery cost
of material to the site. Extra cost to delivery material to the site. Supplier decide the price base on the distance of the place to deliver the material. Material Cost -
If the site is far away from the factory
or warehouse : the delivery cost is more expensive. This increasement happen because of cost unloading the material to the site. Material Cost -
This cost must included to the transportation cost because
it must consider wether it is use labour or mechine like forklift , crane or other machinary. Material Cost -
Storage cost to storage the perishable building materials(can easily
be damaged): like cement, glass, tiles, flammable materilas like woods etc. Purpose to storage: for safety Material Cost -
Wastage and shrinkage or damages cost Easy damages or
substance noy fully utilized materials (not fully used): wastage. estimate for wastage: 10% -15% material on site gone to waste and damage. Material Cost -
Valuation of different waste: Based on on types
of materials, types of work and work efficiency. Wastage is calculated from the order stage until to the construction proces. Material Cost -
basically the value of wastage depend to the types
of the materials: base on percentage: Material Cost -
Material Cost Wastage cost ( % ) i.e :
o cement 5 % o tiles 2% o Timber 5% o Steel 10% -
Labour Cost Introduction: Labour cost is a payment to the
worker after he had completed his work. labour Payment is different based on their experience. Basically there are four(4) types of labour in the market. -
Labour Cost Skill labour Medium labour General
labour Kepala Schedule of rate & Human recourse -
Labour Cost Skill labour- VERY EXPERT in certain work involve
in the trade work: Carpenter Concreter Plumber Bricklayer Plasterer Excavator Tiler Salary - based on day work rate or by hour working day - *8 hour/day- working day Rate- RM 70/day - depend how difficult the work. -
Labour Cost Medium labour- assistant to skill labour -
a lot of work to be done by the same skill labour. Salary – around RM 35.00 - RM 40.00 -
Labour Cost General labour– follow the instruction from skill
labour or medium labour. - do the work like: transport material by manual remove the material site clearing from the surplus Salary- around RM 20 – RM 30 -
Labour Cost Kepala – Leader for the gang or
group of workers: Skill workers, Medium workers, General workers - Responsible to operate and supervise on site the construction work on behalf of the contractor. - very expert in certain field: manage the material on site, tools/equipment,labour. -
Labour Cost Kepala – paid by salary and allocated
in company overhead cost . Salary- around RM 20 – RM 30 Labour constant: -
Labour Cost Labour constant – Average time taken by
the worker to complete their work based on the certain unit. • Skill and labour capacity is not similar to each other. • Skill must be measured by labour constant. • Unit : hour/m, hour/m2 : hour/m3 ,hour/kg : etc. -
Machinery/ Equipment/Tools Manual •Scaffolding •Wheelbarrow • staircase • pail •
etc Machine •Excavator, mixer •Scrapper •Lorry •Crane •etc buy rent buy rent √ x √ √ Overhead cost Capital Cost -
Machinery/Equipment/Tools Machinery/Equipment/Tools cost: Contractor will use various of:
Machinery/Equipment/Tools: purpose: Can be divided into 2 types: • Save time and energy • Non mechanized plant • Mechanized plant -
Machinery/Equipment/Tools Non mechanized plant: Basic tools in building
construction work. Usually owned by the Contractor. • Scaffolding • Ladder • Wheelbarrow • Hand tools • Pail • etc -
Machinery/Equipment/Tools Mechanized plant: Contractor must spend a lot
of money to buy and/or rent the mechanized plant. Depend to the: • Crane • Backhoe • Backactor • Dragline • Excavator Contractor’s financial position Contractor’s requirement: • Continued • occasionally OR -
Machinery/Equipment/Tools Mechanized plant: Capital to buy and rent
these devices should be recalculated to obtain the cost of capital has been issued. How to get back the money used to purchase capital equipment ? It must: -
Machinery/Equipment/Tools Mechanized plant: Get back the money used to
purchase capital equipment: recalculated analyze The price of the use of tools for one hour a day Wage laborers who handle the equipment -
Machinery/Equipment/Tools Method to analyze the Machinery: Analysis equipment
rented: • Include the machinery, driver and fuel. Personal machinery – buy, loan Cost incurred by the contractor are: • Cost depletion for each machinery until it sale by second hand cost. -
Machinery/Equipment/Tools • Cost of lost investment- bear interest • Cost
of maintenance. • Cost of transportation to the site. • Cost of operation –salary the driver and assistant driver, fuel to operate the machine. -
Overhead and Profit Overhead cost: Company overhead cost
is: To manage and administer the staff and the office equipment. • the rate of expenditure incurred by the company • Salaries • Allowance • & other payment to the staff: overtime, bonus, etc -
Overhead and Profit Overhead cost: Building: • Office
rental • Store • Warehouse • Workshop • Non mechanized plant cost • etc. -
Overhead and Profit Overhead cost: Bill: • electricity
• telecommunication • telephone • insurance • Water • Post • Etc. -
Overhead and Profit Overhead cost: Office equipment: •
Office furniture • computer • Photocopy machine • paper • Stationary • Fax • etc. -
Overhead and Profit Overhead cost: Bill for workshop/laboratory
operation: Bill for non machinery tools: • Rent temporary store (if any) • Concrete test bill in any laboratory • Rent workshop for plumbing work • Petty cash: Replace fluorescent lamps Repair damaged sink -
Overhead and Profit Overhead cost: Calculate by percentage
from: • Material cost • Labour cost • Machinery/equipment or tools cost = 5-10% -
Overhead and Profit Overhead cost: Divide: The total
overhead cost for the company. By the average income or money reversal per annum. Example: Income or money reversal for the company/year = RM 1,000,000.00 Overhead cost/year = RM 50,000.00 = 5 -10% -
Overhead and Profit Calculation: Percentage Overhead cost= Overhead cost
Income Percentage Overhead cost= Overhead cost Income = RM 50,000.00 RM 1,000,000.00 = 5% x 100% -
Overhead and Profit Profit cost: To ensure contractor
business can run properly. Company need a bid allowance to support the liability cost management and administration of a contract. -
Overhead and Profit Profit cost: Profit rate calculated
by percentage from: Known as: i. Material cost ii. Labour cost iii. Equipment cost gross profit. -
Overhead and Profit Profit cost: Gross profit consists
of: Percentage taken will vary from one firm to other firm. It depends to the: i. Nett cost ii. Overhead cost gross profit. • Contract size • type of existing workload • contract risk • contract period -
Overhead and Profit Profit cost: Gross profit :5%
Percent profit & Overhead rate is usually between: Nett cost + Overhead cost gross profit. Nett cost + Overhead cost 5% + 5% 10% 10 to 15%