  1. Seasonal Comparison Leaf-off Feb 16, 2010 Leaf-on Nov 9, 2011

    Smith GIS Consortium Google Earth in Smith County, TX
  2. Contributors as of 9/29/2014 BASE Texas Department of Transportation Texas

    Commission on Environmental Quality Railroad Commission of Texas, Surface Mining and Reclamation Division Texas General Land Office BUY-UP University Lands National Geospatial-Intelligence Agency San Antonio River Authority Texas Orthoimagery Program
  3. Cost 4-band (Natural Color & Color Infrared) Orthoimagery Pixel Resolution

    Tiles: Tiles: Mosaic: Per DO4Q Per DOQQ Per County (~1 sq. mi.) (~16 sq. mi.) 0.5-meter (BASE) --------- $151.05 $100 1-foot (BUY-UP) $20.00* --------- $200 6-inch (BUY-UP) $55.00* --------- $200 * Area must be > 600 sq. mi. and contiguous Vendor, Surdex Corp., selected September 2014. Texas Orthoimagery Program
  4. High Priority Imagery and Data Sets Contract HPIDS • Pool

    resources • Lower cost per entity • Higher quality service • Save time – no individual procurements Initiated/held by Council on Competitive Government Administered by TWDB-TNRIS Established 2009 Expires 2015
  5. Deliverables Phased Deliveries Formats GeoTIFF JPEG2000 MrSID Products DOQQs County

    Mosaics QA/QC TNRIS & In-kind option Data storage and distribution – public domain TNRIS Texas Orthoimagery Program
  6. 2014 Timeline 2014/2015 Statewide Leaf-off Orthoimagery Milestone Date Initial Meeting

    February 11 – Complete Public Announcement April – Complete Review Draft Solicitation (SOW) May – Complete Notification of Intent Mid May – Now thru October 15 Finalize Solicitation (SOW) Late May – Complete Release Solicitation (SOW) Mid June – Complete Response Deadline Mid August – Complete Evaluation Early September – Complete Vendor Selection Mid September – Complete Project Kick-Off Meeting Mid October – Next Deadline for participation October 15 – Next PO Deadline November 1 Begin Data Acquisition December 1/Leaf-off conditions Gather Partners Texas Orthoimagery Program
  7. 2015 Timeline 2014/2015 Statewide Leaf-off Orthoimagery Milestone Date End Data

    Acquisition March 15/Leaf-off conditions Orthoimagery Phased Deliveries Summer/Fall QA/QC Phased Approvals Fall/Winter Project Close-Out Winter For questions contact: Gayla Mullins, TNRIS [email protected] 512-463-7104 Texas Orthoimagery Program
  8. Next Steps TNRIS  Introduce publicly StratMap Workshop Website Outreach

     Draft SOW (Solicitation) for partner review  Release SOW to HPIDS vendor pool Gather more partners Partners  Notification of intent  Confirmation of budget approval Gather more partners Texas Orthoimagery Program
  9. Contact Info Gayla Mullins [email protected] POC 512-463-7104 Al Dillard [email protected]

    Procurement 512-463-3154 Texas Natural Resources Information System, a part of the Texas Water Development Board