Upgrade to Pro — share decks privately, control downloads, hide ads and more …

David Hytch

David Hytch

Windfarms - The current and future development challenges

Energy Now Expo 2013

February 14, 2013
Tweet

More Decks by Energy Now Expo 2013

Other Decks in Education

Transcript

  1. Introduction • BVG Associates • What are the development challenges

    for onshore wind developments? • Focus on differences between typical large scale and medium scale wind projects • What are the current development challenges? • What are the likely challenges of the future? • East Ash Farm, Devon; turbine collapsed on 27th January • Winsdon Farm, Cornwall; turbine collapsed on 31st January • Is medium scale wind development worth it? 3 © BVG Associates 2013
  2. BVG Associates Project implementation • FIT project development • Site

    selection • Feasibility studies • Wind speed and energy yield assessments • Project costing and returns • Development and consenting project management • SCADA & condition monitoring • O&M technical support • Turbine performance reviews Market analysis & business development • Supply chain development • Economic impact assessment • Support to industrialisation Technical innovation & engineering analysis • Support to investment in technology • R&D programme management • Design and engineering services 4 © BVG Associates 2012
  3. Photograph courtesy of EWT Planning considerations • Aviation • Noise

    • Birds and bats • Shadow flicker • Landscape and visual • Hydrology and hydrogeology • Archaeology • Transport • Telecoms • Ecology and habitat protection • Public safety 5 © BVG Associates 2013
  4. Site feasibility considerations • Wind monitoring • Access • Topography

    • Ground conditions • Grid connection • Turbine choice • Site designations • Finance and support mechanisms • Unlikely that most of this will be required for medium scale developments 6 © BVG Associates 2013 Photograph courtesy of EWT
  5. Typical large scale project timeline 7 © BVG Associates 2013

    Stakeholder Consultation Planning Application Prep Detailed Civil and Electrical Design Screening and Staged Feasibility Finance and PPA Agreed Grid Connection Agreed Preliminary Design Civil Works Grid Electrical Works Wind Monitoring and Analysis 14 Months 6 Months 4 Months 6 Months 6-12 Months 1 2 3 4 5 Contract Review Lease if third party Typical duration but can be shorter and very much longer Environmental survey Option to develop if third party Final Design Commission, Handover & Operate Scoping and Screening Mast planning permission Planning Application and Approval(?) Appeal – decision 24 months average from application Farm Electrical Works Turbine installation Grid Connection Impact Assessment Pre Consent Detailed Design and Contracting Construction to takeover 3 to 3½ years Turbine Procurement and, Contract negotiation
  6. Typical medium scale project timeline 8 © BVG Associates 2013

    Stakeholder Consultation Planning Application Prep Detailed Civil and Electrical Design Screening and Staged Feasibility Finance and PPA Agreed Grid Connection Agreed Preliminary Design Civil Works Grid Electrical Works 1 2 3 4 5 Contract Review Option to develop if third party Final Design Commission, Handover & Operate Scoping Planning Application and Approval(?) Appeal – decision approximately 7 months from application Farm Electrical Works Turbine installation Grid Connection Pre Consent Detailed Design and Contracting Construction to takeover 1 Month 2 Months 4 Months 2 Months 4-7 Months 13 to 18 months Turbine Procurement and, Contract negotiation
  7. Medium scale “site killers” • Grid connection • Application to

    grid operator • Operator provides best offer • Route and distance to grid are important • Aviation • Estimated up to 2GW stuck in planning due to aviation • Ministry of Defence • Air Traffic Control • Mitigation possible but not usually financially feasible within budgets of medium scale wind projects • Environmental designations 9 © BVG Associates 2013
  8. Future challenges • Cumulative impacts • Increasing planning requirements •

    Public acceptance • Community schemes • FIT tariffs 10 © BVG Associates 2013 0 5 10 15 20 25 0 5 10 15 20 Simple pay back period (years) FIT tariff (p/kWh) Wind speed 6m/s at 40m hub height 1 x 500kW turbine
  9. Project returns – impact of scale 11 © BVG Associates

    2013 0 2 4 6 8 10 12 14 16 0 200 400 600 800 1000 1200 1400 1600 1800 2000 Payback Period (year) Turbine capacity (kW) 1 T, 6 m/s 1 T, 6.5 m/s 1 T, 7 m/s Very dependent on O&M costs and local planning costs e.g. Environmental report Wind Speed at 45 m above ground level
  10. Project returns with FIT support • Assumes FIT tariffs as

    off April 2012 and 10% losses • Wind speed makes a lot of difference • FIT makes 500 kW give a good return but ... • 10 MW project with large turbines generates about just under 20 times more energy than the 500kW project • Two 500kW turbines will give a worse return as it has a lower FIT tariff • SPBP = simple pay back period • IRR = internal rate of return 12 © BVG Associates 2013 Wind project Wind speed at 45m (m/s) 5.5 6.0 6.5 7.0 1 x 500kW (FIT) 40m hub height SPBP (yrs) 4.5 3.7 3.2 2.8 IRR (10 yrs) 18% 24% 29% 34% 5 x 2MW (RO) 80m hub height SPBP (yrs) 7.7 6.3 5.3 4.6 IRR (10 yrs) 5.0% 9.6% 14% 17%
  11. Is medium scale wind development worth it? We can help

    you decide… David Hÿtch [email protected] 01793 752 308 The Blackthorn Centre Purton Road Cricklade Swindon SN6 6HY 13 © BVG Associates 2013